November 2021 Update

Conduit runs have been installed and road subbase has been placed for the access roads along Addison Creek. Concrete has been poured for the access road East of the creek, as well as for sidewalks and curbs near the entrance to the site. Work has begun on the Spillway structure, and the pump station excavation has been completed. Rock excavation continues in the reservoir.